ACG METALS LIMITED: Q1 2026 Operations and Capital Structure Update

PR Newswire
Today at 7:31am UTC

ACG METALS LIMITED: Q1 2026 Operations and Capital Structure Update

PR Newswire

Strong Execution and Project Momentum

LONDON, April 21, 2026 /PRNewswire/ -- ACG Metals Limited (LSE: ACG) ("ACG" or the "Company") is pleased to announce its operations and capital structure update for the first quarter of 2026 ("Q1 2026").

Q1 2026 Summary

  • Lost time injury frequency increased during Q1 2026 as Construction and Mining crews adjusted to the increasing intensity of activity in their respective areas; an emphasis on personal responsibility and safety training drove a downward trend in LTIF, with no LTIs recorded in March, while Project‑to‑Date LTIF remained relatively unchanged at approximately 3.2 LTI per million man‑hours.
  • Total production of 12,168 oz AuEq in Q1 2026, a 22% decrease compared to Q1 2025, as expected and consistent with the mine plan during the transition from oxide to sulphide ore.
  • Year‑on‑year Q1 2026 C1 cash costs decreased by 12% to US$387/oz AuEq compared to Q1 2025, reflecting the processing of stockpiled oxide ore following the completion of oxide mining activities in 2025.
  • AISC increased by 49% to US$1,438/oz AuEq, due to higher royalties resulting from significantly higher realised gold and silver prices.
  • Realised gold and silver prices increased materially in Q1 2026 compared to Q1 2025, rising by 77% and 166% respectively, to US$5,023/oz gold and US$84.4/oz silver, supporting strong revenues.
  • Mining activities during Q1 2026 focused on sulphide ore stripping, with oxide ore mining completed and all oxide material stockpiled by the end of 2025.
  • The Gediktepe Sulphide Expansion Project continues to progress on schedule and within budget, with production in the middle of 2026; as of 31 March 2026, US$101 million, excluding cash advances, has been spent of the total US$146 million.
  • Technical, engineering and procurement activities for the enriched ore project are progressing, with metallurgical test work largely complete, early design commenced and key equipment awarded.
  • Net financial debt as at 31 March 2025 remained low at US$78 million, supported by a strong cash balance of US$122 million, including US$28 million of restricted cash.

Artem Volynets, Chairman and CEO of ACG, said:

"Q1 2026 represents a strong start to the year for ACG, reflecting disciplined execution across operations, projects and prudent balance sheet management. Lower C1 cash costs and strong revenues underscore the quality of the operation, while sulphide stripping and the Gediktepe Sulphide Expansion Project continue to progress in line with plan towards production in the middle of 2026. With a robust financial position and key growth projects advancing on schedule, we are well positioned to deliver a transformational year as ACG transitions into a long‑life copper producer."

Q1 YTD 2026 Operating Summary


All oxide mining was complete at the end of 2025





Q1 2026

vs Q1 2025








Au

oz


9,995

-22 %

Production

Ag

oz


129,408

-46 %

AuEq

oz


12,168

-22 %







Au

oz


9,437

-31 %

Sales

Ag

oz


112,728

-50 %

AuEq

oz


11,334

-30 %







Au

$/oz


5,023

77 %

Realised Price

Ag

$/oz


84.4

166 %







C1 Cash Costs (produced)

$/oz


387

-12 %

Cost

AISC (sold)

$/oz


1,438

49 %

Safety And Sustainability

  • Lost time injury frequency increased during Q1 2026 as Construction and Mining crews adjusted to the increasing intensity of activity in their respective areas. 
  • An emphasis on personal responsibility for safety, risk recognition, and supervisor training produced a downward trend in LTIF with no LTIs recorded in March. 
  • Project-to-Date LTIF remained relatively unchanged at approximately 3.2 LTI/million man-hours.

Oxide Operation

  • No oxide ore mining was undertaken in Q1 2026, following the completion of all oxide mining activities and stockpiling of material by the end of 2025.
  • Total production of 12,168 oz AuEq in Q1 2026, a 22% decrease compared to Q1 2025, as expected and consistent with the mine plan during the transition from oxide to sulphide ore.
  • Gold equivalent sales of 11,334 oz AuEq in Q1 2026, representing a 30% decrease compared to Q1 2025, reflecting the impact of lower production volumes during the 2026 transition period.
  • C1 cash costs in Q1 2026 decreased by 12% to US$ 387/oz gold compared to Q1 2025, reflecting the absence of oxide ore mining activities during the period.
  • Realised gold and silver prices increased materially in Q1 2026 relative to Q1 2025, rising by 77% and 166% respectively, to US$5,023/oz gold and US$84.4/oz silver, supporting strong revenues.
  • AISC increased by 49% to US$1,438/oz AuEq versus Q1 2025, due to higher royalties resulting from significantly higher realised gold and silver prices.

Strong Momentum Continues Across Sulphide Expansion Works

  • Significant progress made in formwork for plinths and the columns that equipment sits on.
  • All major equipment delivered onsite including SAG and Ball Mill.
  • Mill now positioned on its foundations, teams are progressing with structural steel installation and continuing the assembly of key processing infrastructure, including flotation cells and several thickeners.
  • Mining activities during Q1 2026 focused on sulphide ore stripping, in line with the mine plan.
  • The Gediktepe Sulphide Expansion Project continues to progress on schedule and within budget, with production in the middle of 2026; US$101 million, excluding cash advances, has been spent of the total US$146 million.

Enriched Ore Project Underway

  • Key process test work for the enriched ore project is complete, and remaining metallurgical work is ongoing to support upcoming design stages.
  • Early design and engineering activities have commenced under the MOU with CH Engineering, with core layout and flow elements already reviewed.
  • Procurement is moving forward, with the grinding circuit awarded and equipment enquiries underway.
  • Preparation of EPC tender documentation is underway, positioning the Project to move efficiently toward the construction phase.
  • A new Environmental Impact Assessment is being finalised for submission, with all regulatory workstreams progressing in line with schedule.

Capital Structure

  • Financial net debt as of 31 March 2025 remained low at US$78 million, supported by a strong cash balance of US$122 million, including US$28 million of restricted cash.

    Financial net debt is calculated using long‑term borrowings at their contractual value, including the US$200 million Nordic bond, net of cash held on the balance sheet (including cash in bank and escrow), and excludes IFRS timing effects and other non‑debt items.

Inside information

The information contained within this announcement is considered by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No.596/2014 (as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018). On the publication of this announcement via a Regulatory Information Service, such information is now considered to be in the public domain.

Forward looking statements

This announcement may contain certain "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements"). Forward-looking statements are identified by their use of terms and phrases such as "believe", "targets", "expects", "aim", "anticipate", "project", "would", "could", "envisage", "estimate", "intend", "may", "plan", "will" or the negative of those, variations or comparable expressions, including references to assumptions. The forward-looking statements in this announcement are based on current expectations and are subject to known and unknown risks and uncertainties that could cause actual results, performance and achievements to differ materially from any results, performance or achievements expressed or implied by such forward-looking statements. Factors that may cause actual results to differ materially from those expressed or implied by such forward looking statements. These forward-looking statements are based on numerous assumptions regarding the present and future business strategies of the Group and the environment in which it is and will operate in the future. All subsequent oral or written forward-looking statements attributed to the Company or any persons acting on its behalf are expressly qualified in their entirety by the cautionary statement above. Each forward-looking statement speaks only as of the date of this announcement. Except as required by applicable law, regulatory requirement, the UK Listing Rules and the Disclosure Guidance and Transparency Rules, neither the Company nor any other party intends to update or revise these forward-looking statements, whether as a result of new information, future events or otherwise.

The person responsible for the release of this information on behalf of the Company is Artem Volynets, Chief Executive Officer.

For further information please contact:

Thirty Three Communications
Communications Advisor
acgmetals-client-success@thirtythreecomms.com

Berenberg 
Research Analysts
Richard Hatch 
+44 (0) 20 3753 3070 

Joint Broker
Jennifer Lee 
+44 (0) 20 3207 7800 

Canaccord 
Research Analysts 
Tim Huff +44 (0) 20 7523 8374

Joint Broker 
James Asensio /Rory Blundell / Charlie Hammond 
+ 44 (0) 20 7523 4680

Stifel 
Research Analysts 
Alex Bedwany +44 (0) 7788 392045

Joint Broker 
Ashton Clanfield / Varun Talwar 
+44 (0) 20 7710 7600

Cantor Fitzgerald 
Research Analysts 
Puneet Singh +1 (416) 350-8153 

About the Company

ACG Metals is a company with a vision to build a global, high-margin, copper-focused producer with safe, efficient, and sustainable operations.

In September 2024, ACG successfully completed the acquisition of the Gediktepe Mine which is expected to transition to primary copper and zinc production from 2026 and will target annual steady-state copper equivalent production of 20-25 kt. Gediktepe produced 39.2koz of AuEq in 2025. 

ACG's team has extensive M&A experience built through decades spent at blue-chip multinationals in the sector. The team brings a significant network as well as a commitment to ESG principles and strong corporate governance. 

(LON: ACG) (OTCQX: ACGAF) (LON: ACGW) (Xetra: ACG) (Bond ISIN: NO0013414565)

For more information about ACG, please visit: www.acgmetals.com

 

Cision View original content:https://www.prnewswire.com/news-releases/acg-metals-limited-q1-2026-operations-and-capital-structure-update-302748388.html

SOURCE ACG METALS LIMITED